Bernard Street New Build

13/05/2020

Due to tight site constraints, this development had to be built in stages in order to allow goods to be accessed from the road. As a result we had to build the 3 storey unit first, allowing craneage into the heart of the site. This also allowed the first precast staircore to be built. Once our phase 1 works were complete we could then start on phase 2 with the timber kit followed by the second staircore. In effect the main contractor had to work themselves out of the site.